Donald Trump’s renewables permitting freeze is prompting solar companies to find an escape hatch from Nevada.

As I previously reported, the Interior Department has all but halted new approvals for solar and wind projects on federal lands. It was entirely unclear how that would affect transmission out west, including in the solar-friendly Nevada desert where major lines were in progress to help power both communities and a growing number of data centers. Shortly after the pause, I took notice of the fact that regulators quietly delayed the timetable by at least two weeks for a key line – the northern portion of NV Energy’s Greenlink project – that had been expected to connect to a litany of solar facilities. Interior told me it still planned to complete the project in September, but it also confirmed that projects specifically necessary for connecting solar onto the grid would face “enhanced” reviews.

Well, we have the latest update in this saga. It turns out NV Energy has actually been beseeching the Federal Energy Regulatory Commission to let solar projects previously planned for Greenlink bail from the interconnection queue without penalty. And the solar industry is now backing them up.

In a July 28 filing submitted after Interior began politically reviewing all renewables projects, NV Energy requested FERC provide a short-term penalty waiver to companies who may elect to leave the interconnection queue because their projects are no longer viable. Typically, companies are subject to financial penalties for withdrawals from the queue, a policy intended to keep developers from hogging a place in line with a risky project they might never build. Now, at least in the eyes of this key power company, it seems Trump’s pause has made that the case for far too many projects.

“It is important that non-viable projects be terminated or withdrawn so that the queue and any required restudies be updated as quickly as possible,” stated the filing, which was first reported by Utility Dive earlier this week. NV Energy also believes there is concern customers may seek to have their deals for power expected from these projects terminated under “force majeure” clauses, and so “the purpose of this waiver request is thus to both clear the queue to the extent possible and avoid unneeded disputes.”

On Monday, the Solar Energy Industries Association endorsed the request in a filing to the commission made in partnership with regional renewable trade group Interwest Energy Alliance. The support statement referenced both the recent de facto repeal of IRA credits as well as the permitting freeze, stating it now “appears that federal agency review staff are unsure how to proceed on solar projects.” This even includes projects on private lands, a concern first raised by Nevada Gov. Joe Lombardo, a Republican, after the permitting freeze came into effect.

The groups all but stated they anticipate companies will pull the plug on solar projects in Nevada, proclaiming that by granting the waiver, “it will encourage projects facing uncertainty due to recent legislation and federal action to exit the process sooner and without penalty, creating more certainty for the remaining projects.”

How this reads to me: Energy developers are understandably trying to figure out how to skate away from this increasingly risky situation as cleanly as they can. It’s anybody’s guess if FERC is willing to show lenience toward these developers.

 

Jael Holzman

Jael is a senior reporter at Heatmap. Previously, she was an energy and climate policy reporter for Axios and covered energy transition resources for E&E News. She lives in Washington, D.C.